George can do a piece of work in 10 days, paul in 12 days and hari in 15 days. they all start the work together, but george leaves after 2 days and paul leaves 3 days before the work is completed. in how many days is the work completed?
Answers
Given,
George can do a piece of work in 10 day.
So,George can do 1/10 piece of work in 1 day
Similarly,
Paul can do 1/12 piece of work in 1 day
Hari can do 1/15 piece of work in 1 day
Now, Let the work will be complete in x days as per given conditions.
Firstly, work done by George in 2 days = 2/10
Since paul leaves before 3 days of work completed , Therefore, He has worked for (x-3) days
Work done by paul by in (x-3) days = (x-3)/12
Work done by hari in x days = x/15
Now, Total work = 1
George can do a piece in 10 days
⇒ 1 day = 1/10 of the work
Paul can do a piece in 12 days
⇒ 1 day = 1/12 of the work
Hari can do a piece in 15 days
⇒ 1 day = 1/15 of the work
------------------------------------------------------------------------------------------------------------
Amount of work completed by George, Paul and Hari in 2 days:
1 day = 1/10 + 1/12 + 1/15 = 1/4
2 days = 1/4 x 2 = 1/2 of the work
------------------------------------------------------------------------------------------------------------
Amount of work completed by Hari alone in the last 3 days:
1 day = 1/15
3 days = 3/15 = 1/5 of the work
------------------------------------------------------------------------------------------------------------
Amount of work remaining:
1 - 1/2 - 1/5 = 3/10
------------------------------------------------------------------------------------------------------------
Let the number of days Paul work be x
Amount of work completed by Paul and Hari in x days:
1 day = 1/12 + 1/15 = 3/20
x days = 3x/20 of the work
Solve x:
3x/20 = 3/10
30x = 60
x = 2
------------------------------------------------------------------------------------------------------------
Find the total number of days needed:
Total number of days = 2 + 3 + 2 = 7
------------------------------------------------------------------------------------------------------------
Answer: The work is completed in 7 days
------------------------------------------------------------------------------------------------------------