Math, asked by arpit3778, 1 year ago

George can do a piece of work in 8 hours. Paul can do the same work in 10 hours, Hari can do the same work in 12 hours.  George, paul and hari start the same work at 9 am, while george stops at 11 am, the remaining two complete the work. What time will the work complete?

Answers

Answered by TooFree
63

George can do the work in 8 hours

⇒ 1 hour = 1/8 of the work


Paul can do the work in 10 hours

⇒1 hour = 1/10 of the work


Hari can do the work in 12 hours

⇒ 1 hour = 1/12 of the work


Find the amount of work that can be completed in an hour:

⇒ 1 hour = 1/8 + 1/10 + 1/12 = 37/120


Find the amount amount of work completed in 2 hours (9 am to 11 am):

⇒ 1 hour = 37/120

⇒2 hours = 37/120 x 2 = 37/60


Find the amount of work remain:

Work remain = 1 - 37/60 = 23/60


Find the amount of work Paul and Hari can do in an hour:

1 hour = 1/10 + 1/12 = 11/60


Find the number of hours needed for them to complete the rest of the work:

Number of hours needed = 23/60 ÷ 11/60 = 2.09 hours = 2 hours


Find the time the work is completed:

11am + 2 hours = 1 pm


Answer: They will complete the work at 1 pm.

Answered by KrishnaSruthi
23

Answer:

lcm of 8,10,12 is 120

efficiency of :

George is 15

Paul is 12

hari is 10

then

all the 3 work in first 2 hrs

2(15+12+10)+x(12+10)=120

x=2.09

tot time from 9 am is 4.09 or 4

so 1 pm