Math, asked by warrensean121, 1 year ago

Gram Panchayat decided to construct a road in a village, the contract estimates that a number of 25 people can complete the construction in 24 days but five more people willing to join the construction workers how long should the take to complete the job?

Answers

Answered by sumityadav907
1

25*24 = total work= 600 unit

5 more people so

30

Total work / Efficiency

=> 600/30=20 days

Answer....