A can do a work in 45 days . he works at it for 15 days and then , B alone finishes the remaining work in 24 days. find the time taken to complete 80 % of the work if they work together.
Answers
Answer:
A alone can do work in 1 day =1/45
B =1-1/x=24
1x-1=24x
24x-1x=44x=1/23
A and B together one day work =1/45+1/23
Step-by-step explanation:
after that you can solve
Step-by-step explanation:
The time taken to complete 80% of the work if A & B work together is 16 days.
Step-by-step explanation:
A alone can do a work in 45 days
So, work done by A in 15 days = = 15/45=1/3
∴ Remaining fraction of work that is done by B alone = 1 - = ← in 24 days
∴ The whole work will be done by B alone in = 24 × 3/2 = 36 days
Now,
Work done by A in 1 day = 1/45
Work done by B in 1 day = 1/36
∴ Work done by A and B together in 1 day is given by,
= 1/45+1/36
= 5+4/180
= 9/180
= 1/20
If, 1 whole work is done by A and B together in 20 days.
Then, 80% of the work will be done in = 20 * 4/5 = 16 days