Math, asked by shortqueen, 11 months ago

guyzzzzzzzzzzzzzzzzzzzzz
please answer dedo......
.
.
que 9

Attachments:

Answers

Answered by shuddha2705
0
Time taken by gautam= 5 hrs
In 1 hour= 1/5 work
Time taken by Gambhir=6 hrs
In 1 hour= 1/6 work
In 1 hour gautam and Gambhir= 1/5 + 1/6
= 11/30 work
There fore they can do the work in 30/11 hours
=2.7 hours

shortqueen: why you reciprocaled that
shortqueen: please tell