Hari and Lalit can together plant saplings in a field
in 6 days. If Hari works alone, he takes 3 additional
days to plant the saplings. If Lalit was to work alone,
how many days will he need to finish the work?
Answers
Answered by
0
Answer:
9
Step-by-step explanation:
Days taken by Hari and Lalit to plant saplings = 6 days
Days Hari takes if he works alone = 3 extra days
Total days Hari takes to plant saplings = 6 + 3
= 9 days
I hope this helps you :)