harish is twice as productive as Girish and together they finish a project in 18 days. In how many days will Harish alone finish the project.
Answers
Answered by
0
Step-by-step explanation:
12days because 2x+x=3x and 3x=18
x=6
harish =12 days work
girish =6 days work
Answered by
6
Answer:
Let girish productivity = x
Then,Harish productivity =2x
Both productivity 1/18
X+2X = 1/18
3X = 1/18
X= 1/54
Girish takes 54 days alone to finish work
So, harish alone finish the work in 27days
Ans : 27days