8/15 or 0.533333.......
Step-by-step explanation:
1/3 +1/5
8/15
Answered by
1
Answer:
8/15 0f the total work.
Step-by-step explanation:
According to question both have to do the same work.
Let the total work be 1.
Smitha can complete the project in 3 days.(given)
In 3 days work done by smitha = 1
In 1 day work done by smitha = 1/3 (less time, less work)(direct variation)
Anitha can complete the project in 5 days.(given)
In 5 days work done by Anitha = 1
In 1 day work done by Anitha = 1/5 (less time, less work)(direct variation)
Now, Work done by both in 1 day= work done by smitha in 1 day + work done by Anitha in 1 day = 1/3 + 1/5 = 8/15 work
and thats your answer.