Math, asked by indiansmathsworld, 11 months ago

hey guys question for today is

a work can be completed by 40 workers in 40 days. if 5 workers leave every 10 days, in how many days work will be completed?

Guys i am trying to create a mini world for all maths lovers you are requested to follow me and make your contribution

@follow for more ​