hi guys answer it plz
Attachments:
Answers
Answered by
0
Answer:
Step-by-step explanation:
Let one woman takes x days to finish the work.
And one man takes y days to finish the work.
According to the question,
4(2y + 5x) = 1 xy
8y + 20x = xy...(1)
3(3y + 6x) = xy
9y + 18x = xy...(2)
8 36 + 20x = 36x
begin mathsize 12px style 288 over 16 end style= x
x = 18
One woman takes 18 days and one man takes 36 days to finish the work.