Hi please help me here
Attachments:
Answers
Answered by
0
Answer:
7 days
please mark me brainliest
Answered by
0
Answer:
the answer is 21 days not 7
if she would take 3 and half days to complete 1/6th of the work then total time taken should be
3 1/2 =7/2
7/2 × 6
7×3=21
she would take 21 days to complete the project