himanshu & abhisek can paint house in 10 days. abhishek & rahul can paint house in 15. days. rahul & himanshu can paint house in 20 days. in how many days can himanshu paint the house?
Answers
Answered by
70
Answer:
Step-by-step explanation:
(H + A) 1 day work = 1/10
(A + R) 1 day work = 1/15
(R + H) 1 day work = 1/20
2(H + A + R) 1 day work = 1/10 + 1/15 + 1/20
=6+4+3/60 = 13/60
(H + A + R) 1 day work = 13/2 x 60 = 13/120
Himanshu 1 day work = 13/120 - 1/5
= 13 - 8/120 = 1/24
Himanshu will complete work in 24 days
Answered by
20
Answer:
hope it's helpful
Step-by-step explanation:
please please mark it as Brainliest answer