how can estimate in the plan
Answers
Answered by
1
Bottom-up estimating allows you to create anestimate for the project as a whole. Toanalyze from the "bottom up," break larger tasks down into detailed tasks, and thenestimate the time needed to complete each one. ... You can then add up the total amount of time needed to complete the plan.