How many days does it take for 8 people to complete a job that takes 12 people 12 days to complete?
Answers
Answered by
0
Answer:
8 days
Step-by-step explanation:
12 people = 12 days
1 person = 12/12 days
= 1 day
therefore 8 people = 1 x 8 days
= 8 days