how many days will 1440 mens take to dig a trench , if 640 men can do the same in 36 days​

Attachments:

Answers

Answered by nikhilmalpani130
1

Answer:

640 men = 36 days

1440 men = x days. (cross multiplication)

1440*36 = 640*x

51840 = 640x

51840/640 = x

81 = x

hence, 81 days will be taken by 1440 mens.

hope you like it mark me as brainlist :)

Answered by nikhilExpert
3

Answer:

16 days

Thats answer

Check it