how many men need to employee to complete a job in 5 days if 15 men can complete 1/3 of the job in 7 days
Answers
Answered by
2
15 men can complete 1/3 of the job in 7 days
15 men can complete the job in 21 days
x men can complete the job in 5 days
x =
x = 63 men is needed to complete the job in 5 days.
15 men can complete the job in 21 days
x men can complete the job in 5 days
x =
x = 63 men is needed to complete the job in 5 days.
sukhraj616:
options are 20, 21, 45, 63