Physics, asked by shibuu86, 1 year ago

How much work is done in moving a charge of 2 c across two points having a potential difference 12 V?​

Answers

Answered by sam2598
17

Potential difference,V = 12V

Charge ,Q = 2C

V = W/Q

12 = W/2

W = 24 J

Hope This Helps You!

Answered by duragpalsingh
0

Answer:

Work done is 24 J.

Explanation:

Given,

A charge of 2 C  moving across two points having a potential difference 12 V​.

To find: work done

Solution:

Work done can be found by the product of potential difference and charge,

i.e W = VQ

here, V = 12 V and Q = 2 C

Substituting the values,

W = 12 * 2

or, W = 24 J

Therefore, Work done is 24 J.