Science, asked by Khushixi, 7 months ago

How much work is done in moving a charge of 2C across two points having a potential difference of 12 V

Answers

Answered by Barnabas
1

Answer:

24 is the amt of work done

Attachments:
Answered by sannidhya21
6

Answer:

24J

Explanation:

Since, V=W/Q

V=12V

Q=2C

So,

W=VQ

W=12×2

W=24J