How much work is done in moving a charge of 3 C from a point at the volts 115 to a point at 125 volts
Answers
Answered by
5
Potential difference = 125 volts - 115 volts
= 10 volts
Work = Charge × Potential difference
= 3 C × 10 volts
= 30 joules
Work done to move the charge is 30 joules
= 10 volts
Work = Charge × Potential difference
= 3 C × 10 volts
= 30 joules
Work done to move the charge is 30 joules