How to calculate est and lst in project management?
Answers
Answered by
0
Answer:
search in goggle chrome for your favorite app store
you get better results than you get better results and write down your favorite
Answered by
0
Project Critical Path Analysis: Techniques for Scheduling - ITtoolkit EFT of tasks with predecessors = (Task EST + Estimated task duration). On the other side of the coin, latest start (LST) and latest finished times (LFT) are backwards calculations, considering the earliest starting point of the first subsequent task, minus the expected duration of the task under calculation.