Math, asked by anushreeganguly2015, 9 months ago

How to solve sum no 8 from the attachment using unitary method??? Ans-80people

Attachments:

Answers

Answered by TooFree
4

Answer:

336 workers

Step-by-step explanation:

If there were 280 workers:

1/4 of the work = 3 days

Full work = 3 x 4 = 12 days

If there was 1 worker only:

280 workers = 12 days

1 worker = 280 x 12 =3360 days

Find the number of workers needed to complete the work in 10 days:

3360 days = 1 worker

1 day = 3360 workers

10 days = 3360 ÷ 10 = 336 workers

Answer: 336 workers

Answered by RvChaudharY50
11

|| ✰✰ ANSWER ✰✰ ||

It is given that , 280 Heads of People can complete The work in 10 days.

Also Given That, in 3 days These 280 heads of People completed Only (1/4)th of the Total work.

That Means we can say That :- (1 - 1/4) = (3/4)th of The work is Still Left to be done.

And, we have Days Left now = 10-3 = 7 days.

_______________

Lets assume That, now we have X heads of People .

So, Now, with Work out Method we can say That :-

→ if 280 Workers complete (1/4)th of The work in 3 days Than how many workers will complete (3/4)th of the work in 7 days.

→ (M1 * D1 /W1) = (M2 * D2)/(W2)

Putting values now , we get :-

→ ( 280 * 3) / (1/4) = ( X * 7) /(3/4)

Cross - Multiply,

→ 280 * 3 * (3/4) = X * 7 * (1/4)

→ 280 * 9 = 7X

→ 7X = 280 * 9

Dividing by 7 both sides

→ X = 40*9

→ X = 360 Heads of People .

So,

→ Extra Heads of People Required = 360 - 280 = 80 Heads of People.

Hence, 80 More Heads of People Required To complete The work in Time.