Math, asked by kdharithri, 10 months ago

I want the proper solution of this question...if you need 100 points...

Along with this I also need the answer of the following question...
This one is little bit easy. but I need the solution and properly.

Karan and Pavan can complete a job in 40 days and 50 days , respectively. They worked on alternative days to complete it . Find the minimum possible time in which they could have completed it.(in days)
(it can be in fractions also)​

Attachments:

Answers

Answered by Siddharta7
1

Answer:

Option(b) - 2(1/2) hours

Step-by-step explanation:

A and B can fill a tank in 6 hours and 9 hours.

A's 1 - hour work = (1/6)

B's 1 - hour work = (1/9)

Also said that, C can empty the tank in 7.5 hours.

C's 1 - hour work = (1/7.5)

Let it be 'x' hours tap C to be kept open.

Given that,

Tap B is opened 3 hours after tap A is opened.

⇒ 6 * (1/6) + 3 * (1/9) - (x/7.5) = 1

⇒ 1 + (1/3) - (x/7.5) = 1

⇒ (4/3) - (x/7.5) = 1

⇒ -(x/7.5) = -1/3

⇒ -x = 2.5

⇒ x = 2.5

⇒ x = 2 (1/2) hours.

Therefore,

Tap C to be kept open for 2(1/2) hours.

Hope it helps!

Answered by lakshyapatel11255
0

Answer:

A can do in = 40 days

B can do in = 50 days

both can do in = 40×50÷40+50

= 2000/90

= 200/9 days

= 200/9×24 hours

= 533.333333......... hours

This Will be the minimum time working as repeatedly

hope it helps you

please mark as brainliest

Similar questions