If 10 men can dig a pit in 14 days, in how many days can
20 men dig the pit?
Answers
Answered by
10
Answer:
14 × 20 = 280.
280/10 =28.
so 20 men complete there work in 28 days .
please mark me as brainliest....
Answered by
0
Answer:
28 days
Step-by-step explanation:
14×20/10
280/10= 28