Math, asked by zohaibmalik3852, 9 months ago

If 10 men can do a piece of work in 20 days. how long will it take 8 men to do the same job if they work at the same rate??​

Answers

Answered by unicorn276
1

Answer:

Step-by-step explanation:

Total work in units = 40 units ( i.e the LCM of 20,10 and 8)

Rate of work done by 10 people = total work / time taken

Rate of work by 10 people = 40units / 20 days = 2units/day

Rate of work by 1 person = 2 /10 = 1/5

Rate of work by 8 person = 8 × 1/5 = 8/5

Time taken by 8 person = total work / rate of work by 8 person

= 40 units / (8/5) units/day

25 days