If 10 men can do a piece of work in 4 days,
how many men will be required to get the
same work done in 5 days ?
Answers
Answered by
3
Answer:
8 men are required
Step-by-step explanation:
Hope tgat might help you
Answered by
1
Answer:
8 men required
Step-by-step explanation:
let the work done be W
and men required to do it in 5 days be Y
ATQ
W / 10 = 4
W = 10 x 4 = 40 ( 1 equation )
W / Y = 5 ( W is same as work is same )
W = 5Y ( 2 equation )
from 1 and 2 equation
W = W
40 = 5Y
Y = 40/5
Y = 8
8 men are required to do the work in 5 days
I Hope This Will Help You