Math, asked by studentie, 19 days ago

if 10 men can do a work in 8 days how many days will it take 2 men to do the same work?

Answers

Answered by ktejaswini27
1

Answer:

40days

Step-by-step explanation:

10 men's doing x work in 8days.

days required to do the same x work by 2 men

=(10×8)/2

=40

hence 40days