Math, asked by Barbie358, 6 months ago

If 10 men can finish a work in 10 days then in how many days 50 men finish it?
.
.
.
No scams they will be reported

Answers

Answered by mbakshi37
1

Answer:

2 days

work = 10x10

( Learn: this is the way we Know How Much work is there in Man-DaYs)

days = work man = 100/50=2