If 10 men can finish a work in 20 days, in how many days will 20 men finish the same work? *​

Answers

Answered by ARYANTRACKSTAR
0

Step-by-step explanation:

Total work in units = 20 units ( i.e the LCM of 20,10 and 10)

Rate of work done by 10 people = total work / time taken

Rate of work by 10 people = 20units / 20 days = 1units/day

Rate of work by 1 person = 1/10

Rate of work by 10 person = 10 × 1/10 = 1

Time taken by 10 person = total work / rate of work by 10 person

= 20 units / 1 units/day

20 days

Answered by broplayerz621
0

Answer:

10 days

Step-by-step explanation:

If 10 men can do a work in 20 days then 1 man can do it in 10×20 days.

Therefore, 20 men can do it in (20×10)÷ 20 = 10 days