Answered by RabbitPanda
3

Let


x=amount of time it takes 15 men to dig the hole


10 men work at the rate of 1/12 hole per day


1 man works at the rate of 1/120 hole per day


15 men works at the rate of 15/120 hole per day


So, our equation to solve is:


(15/120)x=1 (1 hole, that is)


x=8 days