If 10 men or 20 boys can make 260 mats in 20 days, then how many mats will be made by 8 men and 4 boys in 20 days?
Answers
Answered by
18
Hey .!!
10 men = 20 boys
1 men = 2 boys
8 men = 2*8 boys = 16 boys.
Then,
(16 boys + 4 boys) = 20 boys can make 260 mats in 20 days.
Now,
It can be calculated by work equivalence method:
20*260*20 = x*20*20;
x = 260 mats.
10 men = 20 boys
1 men = 2 boys
8 men = 2*8 boys = 16 boys.
Then,
(16 boys + 4 boys) = 20 boys can make 260 mats in 20 days.
Now,
It can be calculated by work equivalence method:
20*260*20 = x*20*20;
x = 260 mats.