If 10 men working for 4 hrs can complete a work in 6 days how many days would it take for 6 men working 5 hrs a day?
Answers
Answered by
0
Step-by-step explanation:
10 men needs 24 hrs
1 men needs 10*24 hrs
6 men needs (10*24)/6
= 40 hrs
5 hrs a day
40 hrs= 40/5
= 8 days