Math, asked by cloab9965, 1 year ago

If 10 men working for 4 hrs can complete a work in 6 days how many days would it take for 6 men working 5 hrs a day?

Answers

Answered by shuvosaha176817
0

Step-by-step explanation:

10 men needs 24 hrs

1 men needs 10*24 hrs

6 men needs (10*24)/6

= 40 hrs

5 hrs a day

40 hrs= 40/5

= 8 days