If 10 people can do a piece of work in 5 days, working 2 hours a day, how long will 2 people take to do the same work ?
Answers
Answered by
0
Answer:
50 hours. If working for two hours a day then 25 days.
Step-by-step explanation:
2 hours a day for 5 days
So, they work for 10 hours in total.
10 people------------>10 hours
2 people
10 * 10/2
= 50