Math, asked by tvksp202098, 3 months ago

If 10 planters can plant 8 fields in 4 days. How many days are required to plant 18 field by 12 men?

Answers

Answered by sudhjakhar9363
0

Answer:

hshsgwggsjajdjwhgshx

Answered by Barani22
0

Answer:

.

Step-by-step explanation:

12 workers.

8*6=48

x*4=48

x=48/4=12

explanation:

8 (workers) * 6 (hours) = 48 (fixed value - amount of work - no unit)

then:

x (workers) * 4 (hours) = 48

x = 48/4 = 12 (workers)