If 10 planters can plant 8 fields in 4 days. How many days are required to plant 18 field by 12 men?
Answers
Answered by
1
Answer:
15/2 days
Step-by-step explanation:
Given,
If 10 men can plant 8 fields in 4 days.
we know,
work=men*days*hours
here work is plant in fields
8 fields =10 planters*4 days----(1)
How many days are required to plant 18 field by 12 men?
let x be days
18 fields =12 men*x days------(2)
by dividing Eq(1) by (2)
8 fields/18 fields=10 men*4 days/12 men* x days
x=15/2