if 10 workers can build a wall in 12 days, then how many workers will be required to do the same work in 8 days??​

Answers

Answered by ajb7899
6

Answer:

In 12 day wall can be built by = 10 workers

In one day wall can be built by = 10 x 12

In 8 days wall can be built by = 10x12/8

= 15 workers