if 10 workers clean field in 40 days how many days required to clean the field by 20 workers ?
Answers
Answered by
0
use direct and indirect method in maths
Answered by
6
Answer:
10 workers can do it in 40 days
so one worker can do it in 40 into 10 days is equal to 400 days
now 20 workers can do it in 400 divided by 20 days
=20 Days Ans