If 10 workers working for 4hoursComplete the work iñ12days lñ how many days will 8 worker working for 6 hours will complete the same work
Answers
Answered by
1
Answer:
Step-by-step explanation:
simple and short formula,
man X days X hours = work
as work done is same in both cases then
man1 X Days 1 X Hours1=man2 X Days 2 X Hours2
10 X 12 X 4 = 8 X days 2 X 6
solve to get answer.