Math, asked by nikhilislam02, 9 days ago

If 100 men take 15 days to dig a trench 40 metre long, 3 metre wide and 4 metre deep working 8 hours a day, how many men will be required to dig a trench 60 metre long, 8 metre wide and 8 metre deep in 20 days working 12 hours a day.​

Answers

Answered by niranjan100674
0

Answer:

80 days

Step-by-step explanation:

Comparing the two cases, by variation,

= \frac{(men \times days \times hours)}{area of the trench}

areaofthetrench

(men×days× hours)

The above equation is equated,

Hence = \frac{(100 \times 24 \times 8)}{(160 \times 6 \times 4)}

(160×6×4)

(100×24×8)

= \frac{(180 \times x \times 10)}{(450 \times 4 \times 3)}=

(450×4×3)

(180×x×10)

x = 80 days.