if 100 workers can complete a work in 20 days how many workers needed to complete work in 10 days
Answers
Answered by
1
Answer:
200 workers
Step-by-step explanation:
Let, X workers needed to complete work in 10 days
100 workers can complete a work in 20 day
:. 100 workers can complete part of work in a day
:. 1 worker can complete = = part of work in a day
:. 1 worker can complete = = part of work in 10 days
:. To complete work in 10 days = = 200 workers needed