Math, asked by deepti93, 1 year ago

if 1000 men can do a job in 12 days in how many days will 1200men do this job? ​

Answers

Answered by SHARIQ2005
3

1000men=12 days

1 man=12/1000

1200 men = 12×1200/1000

=14.4days


deepti93: day kam hone chahiye na
SHARIQ2005: oh noooo
SHARIQ2005: i did the same mistake in exam
SHARIQ2005: sorryy
SHARIQ2005: will send correct ans in a min
deepti93: ok
SHARIQ2005: 12 men =1000days. 1 man = 12 ×1000 days. 1200 men = 12000/1200 = 10 days
SHARIQ2005: hope it helps
deepti93: ohhhhh
deepti93: thanks alott
Answered by wifilethbridge
1

Answer:

10 days

Step-by-step explanation:

Given :1000 men can do a job in 12 days

To Find : In how many days will 1200 men do this job? ​

Solution:

1000 men can do a job in 12 days

Let x be the number of days to do the job by 1200 men.

So, A.T.Q

1000 \times  12 = 1200 \times x

\frac{1000 \times  12}{1200} =x

\frac{12000}{1200} =x

\frac{120}{12} =x

10 =x

So 1200 men will take 10 days .

Hence 1200 men will do this job in 10 days.