if 12 boys take 3 day to paint a room how long will it take 9 boys to complete the same task
Answers
Answered by
0
Answer:
4 Days
Step-by-step explanation:
By Unitary Method,
WE GET
12 Boys ⟹ 3 days
1 Boy ⟹ 3 × 12 days
9 boys ⟹ 3 × 12
9
= 4 days
THEREFORE, 9 BOYS WOULD TAKE 4 DAYS TO COMPLETE THE SAME JOB