If 12 boys take 3 days to paint a room how long will it take 9 boys to complete the same job
Answers
Answered by
4
9 boys complete the same job in 3 days
Answered by
7
Answer:
4 DAYS
Step-by-step explanation:
By Unitary Method,
WE GET => 12 Boys ------------> 3 Days
1 Boy ---------------> 3*12 Days
9 Boys ------------> 3*12/9 Days = 36/9 Days = 4 Days
THEREFORE, 9 BOYS WOULD TAKE 4 DAYS TO COMPLETE THE SAME JOB