Math, asked by archana0178, 6 months ago

If 12 man can do a piece of work in 36 days. In how
many days 18 men can do the same work?
A. 16 days
B. 20 days
C. 24 days
D. 28 days​

Answers

Answered by wwwmedhu34Medhansh
1

Answer:

12 man = 36

1 man = 36*12

18 man = 432/18

ans- c) 24

Answered by jeetp3969
1
Option C 24days
It is a inverse variation