Math, asked by GodReaper2285, 7 months ago

If 12 men can dig a trench in 66 days how many men will be needed to dig a similar trench in 50 days​.

Answers

Answered by KANHAIYAKUMAR2000000
0

Answer:

Step-by-step explanation:

12 multiply 66 for work done by 1 person then divide by 50 is the resultant number of men required