Math, asked by nnnn12, 1 year ago

if 12 men can do a piece of work in 15 days then 25 men will do the same work in

Answers

Answered by thirumaleshwar
1
6.4 days or 6.7 days they do the total work
Answered by Pranav7818
1
Here I am solving this as unitary method and without language:-
12 MEN-------------15 DAYS
1 MAN---------------15×12 DAYS.I.E. 180 DAYS.
SO,25 MEN-------------180/25 DAYS.

JAI HIND JAI BHARAT PLEASE MARK AS BRAINLIEST