If 12 men can do a piece of work in 18 days, in how many days will 8 men complete it ?
1. 12
2. 27
3. 10
d.⁶-3
Answers
Answered by
1
Answer:
27 is the correct answer
Answered by
0
Answer:
27
Step-by-step explanation:
M1D1 = M2D2
M1=12 , D1=18. M2=8
12*18=8*D2
D2=27