Math, asked by ranjipanigrahi97, 9 months ago

If 12 men can do a piece of work in 18 days, in how many days will 8 men complete it ?

1. 12
2. 27
3. 10
d.⁶-3​

Answers

Answered by rishukumarmittal
1

Answer:

27 is the correct answer

Answered by raju35652
0

Answer:

27

Step-by-step explanation:

M1D1 = M2D2

M1=12 , D1=18. M2=8

12*18=8*D2

D2=27