if 12 men can do a piece of work in 20 days in how many days will 8 men complete it
Answers
Answered by
3
12 : 8 = x : 18
Product of means = product of extremes
12 * 18 = 8x
216 = 8x
x = 216 / 8 , x = 27
8 men can do the same work in 27 days.
Thumps up plz.....
MARK ME AS A BRAINLIEST
Product of means = product of extremes
12 * 18 = 8x
216 = 8x
x = 216 / 8 , x = 27
8 men can do the same work in 27 days.