If 12 men can do a piece of work in 45 days, in how many days will 27 men do the same piece of work?
Answers
Answered by
0
If 12 men can do a piece of work in 45 days, in how many days will 27 men do the same piece of work?
answer is 20 days
Answered by
0
Answer:
20
Step-by-step explanation:
12*45 by 27 =20
I hope it's useful