Math, asked by aarya992, 1 year ago

if 12 men can do a piece of work in 5 days how long will one when take to do it​

Answers

Answered by Anonymous
1

Answer:

Step-by-step explanation:

12* 5 = 60 days

12 man work for 5 days and 1 work is done

so 1 man work for 5 days and 1/12 work is done

now 1/12 work by 1 man in 5 days

so 1 work by 1 man in 5/(1/12) =5*12 = 60 days


aarya992: but how
Anonymous: for a given work as number of people decreases no of days will increase
Anonymous: check now
CuteUnicornRocks: we hv to divide 12 by 5
CuteUnicornRocks: then we will get the answer
Anonymous: do u think if less people will work ; work will complete in lesser days
CuteUnicornRocks: ughhh
CuteUnicornRocks: just leave the matter
CuteUnicornRocks: aarya you decide what the correct answer is
Answered by CuteUnicornRocks
0

the answer is 2.4 Days as we divide 12 by 5