if 12 men can do a work in 15 days. how many men can do the same work in 9 days. how many days will 5 men take to do the same work
Answers
Answered by
1
Answer:
1 man will complete the job in 15×12 days
so 9 men will do 15×12/9=20 days
5 will do 15×12/5=36 days
Step-by-step explanation: