Math, asked by arpansas, 2 months ago

if 12 men can do a work in 15 days. how many men can do the same work in 9 days. how many days will 5 men take to do the same work​

Answers

Answered by Topper1926
1

Answer:

1 man will complete the job in 15×12 days

so 9 men will do 15×12/9=20 days

5 will do 15×12/5=36 days